Subcontracting Opportunities

 

U.T. Austin Experimental Science Building (102-259)

 

 

 

 

 

Affiliation

Contact Name

Contact Number

E-mail Address

 

 

 

 

The Beck Group

Matt Pickens
Project Manager

512-524-1480

mattpickens@beckgroup.com

OHD&FSBP

Orlando Castaneda
HUB/Technical Assistance Coordinator

512-499-4631

ocastaneda@utsystem.edu

 

 

 

 

 

 

 

 

 

 

Bid Package #2 – (demo & abatement, ductbank, thermal utilities , CWR bore)

1/4/08 - Advertise RFP for selection of Pack 2 trade contractors

1/9/08 – Pre-Proposal meeting - Pack 2 trade contractors

1/21/08 – Pre-Proposal deadline - Pack 2 trade contractors

1/29/08 - NTP - Pack 2 trade contractors

 

Bid Package #2A – (excavation & retention system)

02/21/08 - Advertise RFP for selection of pack #2a trade contractors

02/27/08 – Pre-Proposal meeting - Pack #2a trade contractors

03/05/08 – Pre-Proposal deadline - Pack #2a trade contractors

05/15/08 - NTP - Pack #2a trade contractors

 

*The plans and specifications for Pack 2 are the same plans and specifications being utilized for Pack 2a.

 

Bid Package #3 – (foundation & remaining utilities)

 

- Mixer/Outreach for pack #3 trade contractors

Estimated in

- Advertise RFP for selection of Pack #3 trade contractors

June

- Pre-Proposal meeting - Pack #3 trade contractors

 

- Proposal deadline - Pack #3 trade contractors

 

- NTP - Pack #3 trade contractors

 

Bid Package #4 – (exterior & interior build-out)

 

- Mixer/Outreach for Pack #4 trade contractors

Estimated In

- Advertise RFP for selection of Pack #4 trade contractors

August

- Pre-Proposal meeting - Pack #4 trade contractors

 

- Proposal deadline - Pack #4 trade contractors

 

- NTP - Pack #4 trade contractors

 

***These dates are projected dates and are subject to change.  Please contact one of the individuals above to verify actual dates.

  

          

U.T. Health Science Center San Antonio South Texas Research Facility (402-275)

 

 

 

 

Affiliation

Contact Name

Contact Number

E-mail Address

   

Vaughn Construction

Brett Fairman

Project Manager

210-558-9494

bfairman@vaughnconstruction.com

OHD&FSBP

Orlando Castaneda

HUB/TA Coordinator

512-499-4631

ocastaneda@utsystem.edu

 

 

 

 

 

Bid Package #1 – (excavation. site utilities, piers, vivarium structure and parking lots)

To Be Determined – Mixer/outreach for pack #1 trade contractors

05/07/08 – Advertise RFP for selection of pack #1 trade contractors

05/15/08 – Pre-Proposal meeting – pack #1 trade contractors

05/27/08 – Pre-Proposal deadline – pack #1 trade contractors

06/10/08 – NTP – Pack #1 trade contractors

 

Bid Package #2 – (main bldg. slab/structure, curtain walls, and central plant 100%)

To be determined – Mixer/Outreach for pack #2 trade contractors

07/15/08 – Advertise RFP for selection of pack #2 trade contractors

07/23/08 – Pre-proposal meeting – pack #2 trade contractors

08/07/08 – Proposal deadline – pack #2 trade contractors

08/28/08 – NTP – pack  #2 trade contractors

 

Bid Package #3 – (exterior skin)

To be determined – Mixer/Outreach for Pack #3 trade contractors

TBD – Advertise RFP for selection of pack 3 trade contractors

TBD – Pre-proposal meeting – pack #3 trade contractors

TBD – Proposal deadline – pack #3 trade contractors

TBD – NTP – pack #3 trade contractors

 

Bid Package #4 – (MEP and interior build-out main bldg. and vivarium)

TBD – Mixer/Outreach for pack #4 trade contractors

11/21/08 – Advertise RFP for selection of pack #4 trade contractors

12/01/08 – Pre-proposal meeting – pack #4 trade contractors

12/17/08 – Proposal deadline – pack #4 trade contractors

01/14/09 – NTP – pack #4 trade contractors

 

***These dates are projected dates and are subject to change.  Please contact one of the individuals above to verify actual dates.

   

 

 

The University of Texas Biomedical Engineering Building (102-172)

 

 

 

 

Affiliation

Contact Name

Contact Number

E-mail Address

 

 

 

 

Vaughn Construction

Art Serna, Jr.
Project Manager

512-475-8119

artjr@vaughnconstruction.com

Vaughn Construction

Erik Eubank
Assistant Project Manager

512-475-8119

eeubank@vaughnconstruction.com

OHD&FSBP

Shaun McGowan
HUB Coordinator

512-499-4634

smcgowan@utsystem.edu

 

 

 

 

 

 

 

 

Bid Package #1 – (Utilities/Excavation/Foundations))

08/31/08 -  Mixer/outreach for pack #1 trade contractors

09/01/08 – Advertise RFP for selection of pack #1 trade contractors

09/15/08 – Pre-Proposal meeting – pack #1 trade contractors

09/26/08 – Proposal deadline – pack #1 trade contractors

 

Bid Package #2 – (Building Structures/Exterior/Interior Build-Out)

12/19/08 – Mixer/Outreach for pack #2 trade contractors

12/22/08 – Advertise RFP for selection of pack #2 trade contractors

01/05/09 – Pre-proposal meeting – pack #2 trade contractors

01/16/09 – Proposal deadline – pack #2 trade contractors

 

***These dates are projected dates and are subject to change.  Please contact one of the individuals above to verify actual dates.

        

 

 

UT Austin School of Nursing Addition (102-198-1)
       
Affiliation
Contact Name/Title
Contact No. 
E-Mail Address
       
Harvey-Cleary Builders

Clint Morris

Project Manager

512.928.9300
OFPC- HUB

Justin Jones

HUB Coordinator

512.499.4606
 
 
Pack 1 Bid Package - (Fire Protection Code Upgrades)
 - Advertise RFP for selection of tree removal
 - PreProposal Meeting for above trade contractors
 - PreProposal Deadline for above trade contractors
 
Pack 2 Bid Package - (Steel, Curtainwall, Demo, Concrete)
4/21/08 - Advertise RFP for selection of Pack 2 trade contractors
4/23/08 - PreProposal Meeting - Pack 2 trade contractors
5/6/08 - PreProposal Deadline - Pack 2 trade contractors
 
Pack 3 Bid Package - (Interior Build-Out, MEP)
*5/9/08 - Mixer/Outreach for Pack 3 trade contractors
*5/12/08 - Advertise RFP for selection of Pack 3 trade contractors
*5/14/08 - PreProposal Meeting - Pack 3 trade contractors
*5/26/08 - Proposal Deadline - Pack 3 trade contractors
*These dates are projected dates and are subject to change.  Please contact one of the individuals above to verify actual dates.

 

 

 

UT Administration Building Renovation (102-346)

 

 

 

 

Affiliation

Contact Name/Title

Contact No.

E-mail Address

 

 

 

 

Flintco, Inc.

Toby Smith
Project Manager

512-891-7224

tsmith@flintco.com

OFPC – HUB

Stephanie Park
HUB Coordinator

512-499-4378

spark@utsystem.edu

 

 

 

 

 

 

 

 

Bid Package #2 – Generator

04/03/08 – Advertise RFP for selection of pack #2 trade contractors

04/10/08 - Pre-Bid Conference

04/24/08 – Bids Due

 

Bid Package #3 – MCC,  Pumps and Chillers

04/17/08 – Advertise RFP for selection of pack #3 trade contractors

04/23/08 – Pre-Bid Conference

05/08/08 – Bids Due

 

Bid Package #4 – OFPC Finish-Out (Floors 6 & 7)

05/12/08 – Mixer Outreach for Pack #4 contractors

05/20/08 – Advertise RFP for selection of pack #4 trade contractors

05/28/08 - Pre-Bid Conference, 2:00 p.m. (Tentative)

06/10/08 – Bids Due

 

Bid Package #5 – Infrastructure/Core, I-School Finish-Out (Floors 5 & 1)

07/08/08 – Advertise RFP for selection of pack #5 trade contractors

07/09/08 - Pre-Bid Conference, 2:00 p.m. (Tentative)

07/29/08 – Bids Due

 
*These dates are projected dates and are subject to change.  Please contact one of the individuals above to verify actual dates

 

 

Bid Package #4 - Proposal Request

(UT Administration Building Renovations)

 

Project Information:

 

Project Name: UT Austin – UT Administration Building Renovations


Project Location: Austin, Texas


Submit Proposal pricing by: 6/10/08 @ 2:00 PM


Project Description:
Flintco is the CM @ Risk on this project. The project includes the renovation on an existing 8
floor, 253,000 SF building @ 1616 Guadalupe Street. The finish out of floors 6 & 7 scope for
this Bid Package #4 will include the following packages : Final Cleaning, Masonry, Misc. Metals,
Millwork/Running Trim/Casework, Doors/Frames/Hardware, Glazing, Drywall / ACT systems,
Carpet/VCT, Ceramic Tile, Painting, Demountable partitions, Specialties, Signage,
Mechanical/Plumbing and Electrical / Fire Alarm / Telecomm / Security.


Project Schedule:
The schedule for BP #4 includes an anticipated Start of July 2008 and Completion of Nov. 2008.


Pre-Bid, Site Visit:
There will be a pre-proposal meeting on 5/29/08 @ 2:00 PM, at 1616 Guadalupe St, Austin, TX
in the 1st Floor. Pay parking is available in the parking garage on the west side of the Building.
Attendance is STRONGLY ENCOURGAGED for all companies interested in proposing on the
project. This will be the only time for a guided tour of the building and to visit the site and become familiar with the existing job conditions, site access and to discuss project expectations with the CM and the design team.


Plans Availability:


Planrooms: iSqFt, ABC, AGC, Dodge, Builder’s Exchange, City of Austin Department of Small
Minority, and Austin Black Contractor’s Association.


Plans will also be available on 5/20/08 at Flintco’s Austin, Texas office. Please contact Justin
Weaver or Mike Hutter for availability prior to picking up.


Documents will be available in either electronic version (CD), hard copy (paper) plans.


You may also view them at our office located at: 5316 Hwy 290 West, Suite 480, Austin, TX
78735. (Please call for an appointment prior to coming.)

 

The Seal of the University of Texas System

  • © 2007 The University of Texas System
  • 220 West 7th Street
  • Austin, TX 78701-2241
  • Phone: (512) 499-4530
  •