Progress on our new building continues at a steady pace. Here is a picture from Colorado & 7th Street.Exterior view of the new UT System building from 7th Street looking west.

The curtainwall has reached the 19th floor, the chillers have been set on the rooftop, construction on the mechanical penthouse is well underway, and interior mechanical, electrical, plumbing and finish work is active on the office floors.  The east tower crane will be removed in October and the west tower crane will be removed in November / December.  The building is looking spectacular!